#18 Project Update (Thursday morning)

We did not have to replace the last 2 sections of pipe by the lake, which was a huge relief.  They were a little out of round, but were not cracked.  Tying in was a bit challenging due to the slight differences in shape, but we were able to get it done.  At the end of the day yesterday(Wednesday), we had installed the first 20' section and dug back the next 2 sections of pipe.  Things should go much quicker now that the tie in is complete.  We should have a much better idea how much longer that the project will take by the end of the day today.


a view of part of the old pipe crushed and clogged with mud


a pic of the outfall and all of the mud that has migrated into the lake from the pipe


the existing pipe that we tied in to, lined with mud in the bottom


a shot from near the end of the day yesterday