#18 Project Update (Sunday afternoon)

Late yesterday afternoon, we discovered that we will need to replace 2 more sections (40') of pipe.  Those 2 sections will extend us past the cart path, which means that we will now have to remove approximately 35' of the path and re-pour it when finished.  We will also now have to contend with the irrigation main line as well.  We are hopeful that we will be able to complete the pipe installation by late tomorrow afternoon and begin backfilling the trench with dirt and cleaning up immediately afterwards.


a view from inside the pipe of some of the cracks along the top


180' of new pipe has been installed thus far